- Construction and Bond News
Construction & Bond News - CUSD
-
Building to Support AchievementThe Measure A school improvement program, authorized under the passage of Proposition 39, includes modernization and expansion of all schools in the Carmel Unified School District. Some of the key aspects of the program are to optimize state school facilities program funds, minimize learning disruption, promote the arts and physical fitness and maintain safety and quality standards.
See the table below to see the projects made possible by the 2005 bond. Click here to view the Bond Update Newsletters. Click on the links below or in the menu to the left to see pictures of the completed projects.Site
Notice of Completion
2005 General Obligation Bond Proceeds
Other Financing Sources
Total Project Costs
Carmel High School
June 2007
$3,517,474.00
$223,720.00
$3,741,194.00
April 2008
$3,931,672.00
$3,931,672.00
May 2008
$211,249.00
$4,778.00
$216,027.00
March 2009
$4,328,917.00
$4,328,917.00
July 2010
$1,430,297.00
$95,574.00
$1,525,871.00
September 2011
$4,540,227.00
$5,556,098.00
$10,096,325.00
$17,959,836.00
$5,880,170.00
$23,840,006.00
Carmel Middle School
January 2012
$213,633.00
$1,267,685.00
$1,481,318.00
River Elementary School
July 2010
$912,495.00
$86,874.00
$999,369.00
Pending
$132,265.00
$1,567,763.00
$1,700,028.00
$1,044,760.00
$1,654,637.00
$2,699,397.00
Tularcitos
June 2009
$1,354,453.00
$1,354,453.00
Captain Cooper
Improve School Access Road
August 2006
$83,015.00
$71,928.00
$154,943.00
More than One Site
Modify Student Pick-up and Drop off
Various
$40,844.00
$611,711.00
$652,555.00
Temporary Classroom Space
Various
$1,050,163.00
$41.00
$1,050,204.00
General Modernization
Various
$662,615.00
$1,620,265.00
$2,282,880.00
$1,753,622.00
$2,232,017.00
$3,985,639.00
TOTAL
$22,409,319.00
$11,106,437.00
$33,515,756.00